HIGHWAY 1 IMPROVEMENT PROJECT
General Contractor: Kewitt-Flatiron
Sub-trade: Kamloops Augering and Boring
V.I. responsibilities: Fit & welded pipe, 10ft diameter, 1″ wall.
Process: FCAW
The ground at this site was unpredictable; Kamloops Augering encountered a large granite rock which caused significant damage to the pipe. After a month of repairs on both the cutting head and the pipe, the project was completed successfully, although slightly delayed.